Lake Eucha Dam Repairs

Owner: City of Tulsa

System: Dry Shotcrete & Urethane Injection

Completed: 2000

Description:

This job was unique due to the fact that we had to mobilize to reach spalled concrete and cracks on the dam face.  Workers had to actually climb down a ladder on the face of the dam to reach the swing stage rig that allowed for access to repair locations.  Spalled concrete locations along with reinforcing steel were prepped by mechanical means.  Prepackaged concrete material was applied via a dry shotcrete process.  Urethane injection was performed on cracks on concrete face of the dam as well to prevent water leakage.  Upon completion of this project we received the 2000 AGC Merit Award.