ODOT – Seminole & Murray Co

Owner: Oklahoma Dept. of Transportation

System: Dry Shotcrete

Completed: 2013

Description:

The substructure(piers & abutments) on these bridges had began to deteriorate. Spalling of the concrete had occured due to corrosion of the reinforcing steel. Spall locations were sawed & chipped, substrate & steel were cleaned/prepped and a prepackage material was applied to repair spall locations via Dry Shotcrete method.