918-663-1222

Skiatook Dam

Dams

Owner: US Army Corps of Engineers
System: Wet Shotcrete
Completed: 2003

USACE determined that a cover was needed for the Skiatook Dam stilling basin in an effort to keep debris from entering and clogging the basin.   CSC applied approximately 200 cubic yards of concrete, via wet shotcrete method.  The concrete was placed through two mats of reinforcing steel set at 6 inches on center for a total thickness of 18 inches of cover.